Former Tribune Building, Terre Haute, Indiana
-Terre Haute Candlewood Suites Progress-
Former
Tribune Building:
-History
-Artifacts
-Interior
-Progress
-The New Hotel
email me

Recent Activities:

Dec. '06 - Structural Testing (Interior and Exterior)

Jan. '07 - Salvage Work to Interior

Feb. '07 - City Council approves $1.3 Million Bond  
                Incentive

Feb. 23 - Environmental work...white suits, red 
               barrels, BIRD SEED...chuckle.  Also, a 
               small service pit in the basement full of oil,
               ink, and waste water to pump out, clean,
               and fill.  Nothing the pros can't handle  
               though!  Anxious to see this project move
               forward.

Mar. '07 - Service Pit pumped out

Apr. '07 - T-T goes to "Closing"; Design Work Continues

May '07 - (2nd) - Theater emptied of contents
                         - Fence installed
  - Bank of windows removed from 6th 
                           floor of Trib
                         - Old National Bank Announces gift of 
                           $200,000 toward Children's Museum
                         - Interior demo of former Trib under way
                (3rd) - Demolition of Liberty Theater to begin
                (7th) - Remainder of theater fenced in
  - Awning removal continues
              (11th) - Demo well under way

June '07 - (1st)    - Liberty Theater Gone
                 (7th)   - Fire escape removed
                 (16th)   - Liberty/Grand Clean Up Continues
                             - Trib gutting down to 2nd floor now

July '07 - (31st)- Trib gutting down through 1st floor
                                 and into basement; heavy equipment
  and scrap removal from basement.

Dec. '07  - (3rd)  -  Construction Begins!
                (5th)  -   Groundbreaking Ceremony! - 11am

Jan. '08 - Floor Prep, Patching, Leveling
             - Steel reinforcements added in back
             - Elevator replacement

Feb. '08 - South exterior enclosure
  - Interior Framing (6th Floor)
  - Ground Floor Walk-In Vault Demolished

Mar. '08 - Interior Framing, Electrical, Plumbing
   2nd-6th Floors, Floor Repairs, Facade Restoration
   Begins
  - Drywall and Children's Museum Begin Soon

May '08 - Drywall, plumbing, electrical continue
   More floor repairs, facade restoration
   Roofing Begins
   Utilities Hooked Up
   Elevator Work Begins
   New Stairwells Underway
   Children's Museum Foundation Begun!
   Painting Began on 5th and 6th

Oct. 9, 2008 - The Hotel is Open for Business!

-SEE THE BEFORE AND AFTER PICS HERE!